Your Pool Contractor Stopped Showing Up: What to Do in the First 10 Days (California)

Video by Randy Beard · Construction Defects & Forensic Analysis · 8:13 min · Published 2026-11-18

What this video covers

The builder is gone, half the money is paid, and there is a hole with steel in it. The order to do things in: stop paying, document the work in place, fence it and manage the water, find out which subcontractors are owed, and do not terminate or let a replacement cover the work until an attorney and an independent evaluation say go.

Abandoned ProjectsMechanics LiensWork-in-Place Evaluation

Transcript

In California, a pool builder is allowed to take no more than $1,000 as a down payment. And if yours has stopped showing up, what you do in the next 10 days has a lot to do with how much of your money you ever see again. The crew has not been there in two weeks. The calls go to voicemail. You have paid half, or more than half, and what you have is a dangerous open excavation with steel in it, or a bare concrete shell. The state contractor's board has a name for this, front loading. A builder asks for 50% of the total price when the concrete shell is sprayed, but they have only done about 15% of the work. Then they read the job. There is a business reason behind stories like this. Trade Press reports that new in-ground pool construction has dropped by about half since the 2021 peak. When the work drops by half, a builder counting on high volume runs short of cash, and the next customer's payment ends up covering the last customer's concrete.

I'm Randy Beard. I've been building and inspecting pools in California since 1979, and most of my work now is as an expert witness on pool jobs that went wrong. When a builder walks off, I'm the one who gets called to work out what was really built, and what it's going to cost to finish. So here's the order I'd do things in, if it were my backyard. Step 1. Stop paying. Make no further payments to the builder. California law dictates that, apart from the down payment, the builder has no further payments to the builder. So the builder has to pay for a mortgage or mortgage payment. Ah, that's a pretty good one. A contractor may not ask for or accept a payment that is more than the value of the work performed or the material delivered. If a construction lender is funding your project, you must tell that lender in writing today so they do not release another draw.

Step 1. No cleanup. Put a total freeze on the physical site. Do not touch anything. And do not let anyone else touch anything. That means no cleanup, no backfilling the dirt, and no quick fixes by a well-meaning friend. Step 2. Restore the structure. Start a new house. You'll have to build a new home and build a new apartment. Start a new home. Start a new home. You'll have to build a new apartment. You'll have to build a new home. Start a written log immediately. Record the last day anyone worked, exactly who was on site, and what was said. From this point forward, you communicate strictly in writing. Before anything on the site changes, aggressively photograph and video everything with a visible date stamp. Start with wide views of the art. Then document every wall, the floor, the top edge, and every single pipe stub sticking out of the ground. If the steel is still exposed, place a physical tape measure across the rebar grid and photograph the spacing. Once concrete or plaster covers that steel, nobody can verify the spacing without drilling into the shell.

Take that tape measure to the hole itself. Measure the length, width, depths, and steps, and compare those exact physical dimensions against your contracted plan. Now organize your paperwork. Create pile 1, your signed contract, the plans, the payment schedule, and every written change order. Create pile 2, proof of every payment you made. You need images of the front and back of every canceled check. Your entire legal case hinges on the gap between these records, what was promised in pile 1, what was paid in pile 2, and the tape measured reality sitting in the ground. An open excavation is a severe fall hazard. Install a sturdy temporary fence with a locked gate immediately. And call your local building department to ask exactly what barrier they will find. You will find that the fence is closed so you don't have to worry about those barriers. Also, this is one of the best ways to avoid risk of the concrete crash.

And now, let's go to the next point. Keep all surface rainwater draining away from the excavation. Keep any relief valves working. Cap the open PVC pipe ends to protect the plumbing. If that concrete shell floods, get highly qualified advice because this is where you get a better result. Keep all surface rainwater draining away from the excavation. Keep any relief valves working. And cap the open PVC pipe ends to protect the plumbing. If that concrete shell floods, get highly qualified advice. If you don't have any relief valves, before anyone pumps it dry during wet weather. A tarp is not a plan. Next, look up your builder on the State Contractors Board website.

Take a screenshot of their active bond status with the date showing. Know what that bond is. Every licensed contractor carries a $25,000 license bond. It is one bond shared by every customer with a claim. It is not $25,000 for each job. Then contact the building department and ask for the permit expiration date in writing. Go through your mail and pull out every preliminary notice. These are the documents sent by the subcontractors and suppliers who delivered materials or labor to your home. The State Board is clear on this point. The homeowner is ultimately responsible for unpaid suppliers. This is true even if you already paid your prime builder for those materials.

And there is a clock. A job that simply stops is generally treated as complete after six months. You can do this for 60 days with no labor. From there, a subcontractor or supplier generally has 90 days to record a lien against your house. Have an attorney put those dates on a calendar. However, do not pay a subcontractor directly and do not sign any lien release they hand you until a construction attorney has reviewed it. Send the builder a calm, factual letter by regular and certified mail. State exactly what is unfinished, what you want done, at a firm completion date. Here is the most common mistake owners make. Do not send a text message saying you're fired and do not physically lock the builder out of the site.

The contract has its own strict rules for providing notice and a chance to fix the problem. If you terminate the builder improperly, you can accidentally become the party who broke the contract. Take your two organized piles of paper to a California construction attorney. Ask them to properly calendar your mechanics lien deadlines from the last day of labor to the day after. Last day of labor on your site. Ask the attorney about starting your administrative remedies, filing a free complaint with the State Contractors Board, and opening a claim against the builder's license bond. Know the limits. The board itself says it cannot guarantee that you get your money back.

It does run a free arbitration program. It is mandatory for disputes of $25,000 or less and voluntary up to $50,000. Before you hire a replacement, get an independent evaluation of the existing work to solicit new pits. But tell the new crew strictly, nothing gets covered, demolished, or altered until every inch of the old plumbing and rebar has been inspected. That evaluation should give you three lists, work that is complete and acceptable, work that is defective, and work that was simply never finished. The cost to finish, compared with what is still unpaid on the contract, is the core of your claim. Let's review the five rules. Rule one, stop paying the day the work stops.

Rule two, photograph and measure the site with a physical tape measure before anything is touched. Rule three, fence the hazard and actively manage the rainwater. An empty shell and a wet winter do not mix. Rule four, pull all preliminary notices to find out who else is owed, so you do not end up paying twice. Rule five, do not fire the builder and do not let a new crew cover the work, until a construction attorney says go. A hole in the yard is a fact. What you are owed is a number, and the number comes from the photographs, the measurements, and the paper. Control the chaos, organize your documents, and you protect your path to recovery. If you're the homeowner, stop the money, take the pictures, and don't fire anybody by text message.

If you're the attorney getting this call, get somebody out there before the next contract or covers the steel. The claim is the difference between what was paid and what's in the ground, and you can only measure that while you can still see it. Get it documented first.

Transcript made from the video's narration and lightly corrected for technical terms. Watch on YouTube. Free to cite or share.